Dredging at Leijgraaf phase 2
Commissioned by Waterschap Aa en Maas and under project management provided by Kybys, Kurstjens has mechanically dredged around 7 kilometres of the Leijgraaf. This has included over 19,000 m3 of dredge spoil being excavated and spread onto adjacent plots. Part of the dredge spoil has been removed using an axle to an external processing site. What was exceptional in the case of this project was the fact that Kurstjens took care of interactions with the plot owners itself and that the Waterschap did not receive one single complaint during these works.